Public Works | Construction Projects: 2012

Capitol Drive

Reclamation: McCarthy to Mayflower. This project consists of milling the existing surface and widening the road to include paved shoulders for bike lanes.  The road will be 32 feet of pavement with 2-foot aggregate shoulders.

Projected Start Date: July 2012
Bid Due Date: February 8, 2012
Final Resolution: July 3, 2012
Contractor: Not Awarded Yet
Project Manager: McMahon & Associates

 

Casaloma Drive

Concrete Panel Replacement: Wisconsin Avenue to Grand Market Drive. This project consists of replacing deteriorated concrete panels.  This section of road was put in when the mall was built in 1988 and has had no maintenance done since that time.

Bid Due Date: January 24, 2012
Final Resolution: February 7, 2012
Projected Start Date: April 11, 2012
Projected Completion Date: May 5, 2012
Contractor: Corner Stone Pavers
Project Manager: Graef-USA

Bid Tabs: Casaloma Drive document-pdf.png

 

 

Century Farm Estates

This project consists of placing the final asphalt surface on road and also adjusting any manholes as necessary.

Projected Start Date: May 29, 2012
Approximate Project Duration: 4 to 5 days
Bid Due Date: February 8, 2012
Final Resolution: February 23, 2012
Contractor: MCC, Inc.
Project Manager: McMahon & Associates

Bid Tabs: 2012 Paving Projects document-pdf.png

 

 

College Avenue Frontage Road (N)

North side: Westhill Blvd to Lilas Dr. This project consist of asphalt reconstruction of the roadway along with curb and gutter and storm sewer construction.

Projected Start Date: May 2012
Bid Due Date: February 29, 2012
Final Resolution: March 6, 2012
Contractor: Not awarded yet
Project Manager: McMahon & Associates

 

College Avenue Frontage Road (S)

South side: Bluemound Dr to Lilas Dr. This project consist of asphalt reconstruction of the roadway along with curb and gutter and storm sewer construction.

Projected Start Date: May 2012
Bid Due Date: February 29, 2012
Final Resolution: March 20, 2012
Contractor: MCC, Inc.
Project Manager: McMahon & Associates

Bid Tabs: College Avenue Frontage Road (S) document-pdf.png

 

 

Glen Creek Subdivision

This project consist of full urbanization of the subdivision.  Asphalt reconstruction of the roadway along with curb and gutter and storm sewer construction will be done.  Street lights will be added throughout the subdivision with the same type of lighting currently in the subdivision.

Projected Start Date: May 2012
Bid Due Date: February 29, 2012
Final Resolution: March 20, 2012
Contractor: MCC, Inc.
Project Manager: McMahon & Associates will post weekly updates and pictures of the project on their website.

Bid Tabs: Glen Creek Subdivision document-pdf.png

Letter to Glen Creek Residents document-pdf.png

 

 

Glendale Ave and Rexford Street

This project consist of full urbanization of the two streets.  Asphalt reconstruction of the roadway along with curb and gutter and storm sewer construction will be done.

Projected Start Date: April 4, 2012
Projected Completion Date: June 15, 2012
Bid Due Date: January 19, 2012
Final Resolution: March 6, 2012
Contractor: Northeast Asphalt, Inc.
Project Manager: Omnni Associates

Bid Tabs: Glendale Ave and Rexford Street document-pdf.png

 

 

Lynndale Drive (CTH A)

Reconstruction: Nordale Drive to Wisconsin Avenue. This project consists of full road reconstruction with curb and gutter, sidewalk construction, trail construction and storm sewer construction.  This project is a joint collaboration with Outagamie County.

Bid Due Date: January 10, 2012
Final Resolution: February 7, 2012
Projected Start Date: April 16, 2012
Projected Completion Date: October 31, 2012
Contractor: Ptshaniki
Project Manager: Outagamie County | Call 832-5673 with any questions.

 

McCarthy Road

Reclamation: Century Farms Subdivision to Edgewood Dr. This project consists of milling the existing surface and paving the road to the same width.  The road will be 24 feet of pavement with 2-foot aggregate shoulders.

This project has been removed from the 2012 construction project list. It is currently being reviewed by the Town Board and the Department of Public Works.

Projected Start Date: May 2012
Bid Due Date
: February 8, 2012
Final Resolution to Town Board
: February 23, 2012
Contractor
: Not Awarded Yet
Project Manager: McMahon & Associates

Bid Tabs: 2012 Paving Projects document-pdf.png

 

 

Prospect Court

Reclamation: CTH BB to Cul-de-sac. This project consists of milling the existing surface and paving the road to the same width.  The road will be 24 feet of pavement with 2-foot aggregate shoulders.

Projected Start Date: May 14, 2012
Approximate Project Duration: 4 to 5 days
Bid Due Date: February 8, 2012
Final Resolution: March 6, 2012
Contractor: MCC, Inc.
Project Manager: McMahon & Associates

Bid Tabs: 2012 Paving Projects document-pdf.png

 

 

Starview Heights

First Addition. This project consists of placing the final asphalt surface on road and also adjusting any manholes as necessary.

Projected Start Date: May 29, 2012
Approximate Project Duration: 8 to 10 days
Bid Due Date: February 8, 2012
Final Resolution: February 23, 2012
Contractor: MCC, Inc.
Project Manager: McMahon & Associates

Bid Tabs: 2012 Paving Projects document-pdf.png

 

 

Systems Drive

Reclamation: Tri-Park Way to cul-de-sac. This project consists of milling the existing surface and paving the road to the same width.  There will some curb and gutter replacement where it has deteriorated.  The road will be 42 feet of pavement with curb & gutter on both sides.

Projected Start Date: May 16, 2012
Approximate Project Duration: 4 to 5 days
Bid Due Date: February 8, 2012
Final Resolution: March 6, 2012
Contractor: MCC, Inc.
Project Manager: McMahon & Associates

Bid Tabs: 2012 Paving Projects document-pdf.png

 

 

White Hawk Meadows III

This project consists of new construction of sewer and water mains.

Bid Due Date: January 13, 2012
Projected Start Date: February/March 2012
Contractor: PTS Contractors
Project Manager: Davel Engineering

Bid Tabs: White Hawk Meadows III document-pdf.png

 

 

Williams Street Lift Station

Rehabilitation and extension of sanitary sewer lift station.

Bid Due Date: March 6, 2012
Projected Start Date: to be determined
Contractor: to be determined
Project Manager: Town of Grand Chute

Bid Specs: Williams Street Lift Station document-pdf.png 3 MB

 

 